LANDFILL CONSTRUCTION
Lemoine Industrial has successfully completed Type 1 & Type II landfill construction and closure projects for industrial, private and government entities. We have the expertise to understand the intricacies of bidding & managing these complex projects.
HOW WE DO IT
Of the estimated 251 million tons of consumer solid waste generated each year in the U.S., approximately 32.5 percent of the trash is recycled or composted, 12.5 percent is burned and the remaining 55 percent is buried in landfills. When planning the construction or expansion of a landfill proper consideration of the various factors involved in the actual construction can minimize project delays and reduce additional costs.
SERVICES TO CUSTOMERS
♦ New cell construction
♦ Cap /closure
♦ Leachate collection system
♦ Geo-synthetic liners
♦ Hazardous waste cell closure
PROJECTS
NEW CELL CONSTRUCTION: CITY GOVERNMENT
Stage 1 Construction of Harold Landry Landfill: St. Mary Parish (Berwick, LA)
Overall scope included site prep, haul roads, emission controls, perimeter levee construction, SWPPP & site specific H&S plan.
- Excavation / 66,800
- Compacted Clay Liner / 84,780
- HDPE Subsurface Drainage System
- Leachate Collection Installation
- 43,000 cyds Sand Drainage
- 1,170,300 sqft of Geocomposite Drainage Layer
NEW CELL CONSTRUCTION: CITY GOVERNMENT
West Carroll Parish Police Jury: Cell 14 Expansion (Oak Grove, LA)
A lesser project in size and area (4 acres) but one that would require flexibility and precise construction planning to meet a demanding schedule. General scope of work included:
- Site Prep & Dewatering
- Trench Excavation & Shoring
- Compacted Fill & Sand Layer
- Gas Collection System
- Geosynthetic Liner Install
- Leachate Collection Piping
CAPPING & CLOSURE: INDUSTRIAL
Vicksburg Chemical / Arcadis Engineering: Site Decommission (Vicksburg, MS)
Project called for the installation fo two landfill caps along with site health and safety plans, at the former Vicksburg Chemical Plant covering approximately 20 acres.
- 18 Acres of Clay Capping
- 2 Acres of HDPE Liner Capping
- Compacted Clay Liner / 80,000 cyds
- GeoSynthetic Liner Installation
SITE EXPANSION: PRIVATE
Environmental Operators: Cell 3 & 4 Expansion (Venice, LA)
Cell 3 &4 expansion for the City of Venice
- Muck Excavation and Dewatering
- Compacted Clay Liner
- Geocomposite Drainage Net
- Leachate Collection System