Industrial Projects
Cooling Tower Maintenance / Dow Chemical (Plaquemine, LA) June ’08 / 250K
This turnaround project took place at the Glycol Unit where the existing cooling tower was beginning to fail. The plan was simple, once the tower was taken out of operation an intense effort would be required to remove the accumulated debris. Lemoine incorporated 2 crews of 8, on a 24/7 schedule to successfully clean the tower using a "filter press" method hand-in-hand with manual labor.
Personnel: Project Foreman, HAZWOPPER Tech’s, Plant Engineer, and Truck Operators
Equipment: Filter Press, Frac-tanks, Roll-off boxes, 3” pump, Haul Trucks and Skid Steer
Plant Demolition / Arcadis (Vicksburg, MS) Aug ’08 / 250K
Working as a Subcontractor, LI was charged with the demolition for a decommissioned plant, Vicksburg Chemical. All material was hauled to a designated landfill. Site was redressed for new project, the Mississippi Industrial Park.
Personnel: Site Superintendent, HAZWOPPER Tech’s, Heavy Equipment Operators, Flaggers & Truck Drivers
Equipment: 2 Excavators, Dozer, 2 Skid Steers, Roll-off Boxes and Haul Trucks
Dow / Union Carbide (Hahnville, LA) On-going / Various
Lemoine currently provides an on-going service to the Hahnville site for crushing and disposing of the Plants chemical drums. Drums are crushed on site, placed on pallets and shipped to an approved landfill.
Personnel: Foreman and HAZWOPPER Tech’s
Equipment: Industrial Drum Crusher, Fork-lift and Roll-off Bins